Dept. of Trans. PROGRESS Serial No. Contract No. 24-326-14-12 03-1J2604 PROGRESS PAYMENT VOUCHER %complete: %time: 77% 71% Location: Federal Project: 03-NEV-80-16.3/18.8 NONE Progress payment No. 003 Payment period ending: 11-20-24 M A STEINER CONSTRUCTION INC 8854 GREENBACK LN #1 ORANGEVALE CA 95662 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 613,260.75 83,951.00 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 613,260.75 83,951.00 5. Mobilization 6. Total Work Completed 613,260.75 7. Deductions -4,000.00 -4,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 609,260.75 79,951.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 79,951.00