Dept. of Trans. PROGRESS Serial No. Contract No. 23-167-08-44 03-1J8504 PROGRESS PAYMENT VOUCHER %complete: %time: 22% 36% Location: Federal Project: 03-PLA-5731-0.0/50.7 NONE Progress payment No. 002 Payment period ending: 06-20-23 P N P CONSTRUCTION INC 100 CROTHER RD APPLEGATE CA 95703 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 154,707.78 154,707.78 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 47,464.00 0.00 4. Earned Subject to Retention 202,171.78 154,707.78 5. Mobilization 6. Total Work Completed 154,707.78 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 202,171.78 154,707.78 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 154,707.78