Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 21-223-15-22 03-1J9204 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 03-BUT-70-154.0/15.4 NONE Progress payment No. 001 Payment period ending: 06-11-21 MCM CONSTRUCTION INC 6413 32ND ST NORTH HIGHLANDS CA 95660 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 3,600.00 3,600.00 2. a. Extra Work 262,006.06 262,006.06 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 265,606.06 265,606.06 5. Mobilization 6. Total Work Completed 265,606.06 7. Deductions -20,000.00 -20,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 245,606.06 245,606.06 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 245,606.06