Dept. of Trans. PROGRESS Serial No. Contract No. 24-233-08-59 03-1N2504 PROGRESS PAYMENT VOUCHER %complete: %time: 80% 100% Location: Federal Project: 03-PLA-65-137.0/15.1 NONE Progress payment No. 001 Payment period ending: 08-20-24 LAMON CONSTRUCTION CO INC 871 VON GELDERN WAY YUBA CITY CA 95991 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2. a. Extra Work 358,846.66 358,846.66 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 358,846.66 358,846.66 5. Mobilization 6. Total Work Completed 358,846.66 7. Deductions -10,000.00 -10,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 348,846.66 348,846.66 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 348,846.66