Dept. of Trans. FINAL Serial No. Contract No. 24-358-10-01 03-1N2504 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 03-PLA-65-137.0/15.1 NONE Progress payment No. 003 Payment period ending: 08-21-24 LAMON CONSTRUCTION CO INC 871 VON GELDERN WAY YUBA CITY CA 95991 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 3,683.00 0.00 2. a. Extra Work 366,708.19 5,922.26 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 370,391.19 5,922.26 5. Mobilization 6. Total Work Completed 370,391.19 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 370,391.19 5,922.26 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 5,922.26