Dept. of Trans. PROGRESS Serial No. Contract No. 11-203-11-18 03-2A6904 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 10% 6% 03-NEV-49-9.7/11.2 Federal Project: SARR-P049(148) A-P049(148) Progress payment No. 03 Payment period ending: 07-20-11 DE SILVA GATES CONSTRUCTION P O BOX 2909 DUBLIN CA 94568 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 386,140.15 292,854.15 2.a. Extra Work 16,496.98 10,258.00 b. Adjustment Comp. 21,110.28 10,484.00 3. Materials on Hand 4. Earned Subject to Retention 423,747.41 313,596.15 5. Mobilization 419,500.00 419,500.00 6. Total Work Completed 843,247.41 7. Deductions -5,000.00 -5,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 838,247.41 728,096.15 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 728,096.15