Dept. of Trans. SEMI-FINAL Serial No. Contract No. 14-176-14-10 03-2A6904 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 03-NEV-49-9.7/11.2 Federal Project: SARR-P049(148) A-P049(148) Progress payment No. 40 Payment period ending: 03-28-14 DE SILVA GATES CONSTRUCTION P O BOX 2909 DUBLIN CA 94568 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 7,541,225.79 0.00 2.a. Extra Work 936,405.27 0.00 b. Adjustment Comp. 594,978.07 -8,173.14 3. Materials on Hand 4. Earned Subject to Retention 9,072,609.13 -8,173.14 5. Mobilization 839,000.00 0.00 6. Total Work Completed 9,911,609.13 7. Deductions -2,130.00 10,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 9,909,479.13 1,826.86 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,826.86