Dept. of Trans. PROGRESS Serial No. Contract No. 06-169-12-16 03-2A8304 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 93% 98% 03-SAC-80-M0.4/R11.1 Federal Project: ACIM-X067(66) Progress payment No. 14 Payment period ending: 06-16-06 GRANITE CONSTRUCTION COMPANY P O BOX 50085 WATSONVILLE CA 950775085 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2,167,434.00 15,900.00 2.a. Extra Work 107,980.42 3,084.85 b. Adjustment Comp. -5,240.00 -5,240.00 3. Materials on Hand 4. Earned Subject to Retention 2,270,174.42 13,744.85 5. Mobilization 248,000.00 0.00 6. Total Work Completed 2,518,174.42 7. Deductions -18,000.00 -8,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 2,500,174.42 5,744.85 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 5,744.85