Dept. of Trans. PROGRESS Serial No. Contract No. 15-264-14-08 03-2A9204 PROGRESS PAYMENT VOUCHER %complete: %time: 50% 64% Location: Federal Project: 03-PLA-89-0.0/T8.5 ACST-P089(102) P-P089(102) Progress payment No. 023 Payment period ending: 09-20-15 ROAD AND HIGHWAY BUILDERS LLC PO BOX 70846 RENO NV 89570 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 13,584,516.53 1,797,011.32 2. a. Extra Work 809,059.29 62,220.38 b. Adustment Comp. -246,313.22 -56,388.05 3. Materials on Hand 271,257.35 -10,249.98 4. Earned Subject to Retention 14,418,519.95 1,792,593.67 5. Mobilization 3,230,000.00 0.00 6. Total Work Completed 17,377,262.60 7. Deductions -25,194.65 -20,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 17,623,325.30 1,772,593.67 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,772,593.67