Dept. of Trans. PROGRESS Serial No. Contract No. 16-298-13-52 03-2A9204 PROGRESS PAYMENT VOUCHER %complete: %time: 86% 91% Location: Federal Project: 03-PLA-89-0.0/T8.5 ACST-P089(102) P-P089(102) Progress payment No. 033 Payment period ending: 10-20-16 ROAD & HIGHWAY BUILDERS LLC PO BOX 70846 RENO NV 89570 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 25,785,874.56 1,838,832.45 2. a. Extra Work 1,230,565.84 63,710.09 b. Adustment Comp. -953,564.92 -154,234.41 3. Materials on Hand 171,261.00 -150,588.62 4. Earned Subject to Retention 26,234,136.48 1,597,719.51 5. Mobilization 3,400,000.00 0.00 6. Total Work Completed 29,462,875.48 7. Deductions -5,372.40 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 29,628,764.08 1,597,719.51 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,597,719.51