Dept. of Trans. PROGRESS Serial No. Contract No. 17-207-12-41 03-2A9204 PROGRESS PAYMENT VOUCHER %complete: %time: 91% 98% Location: Federal Project: 03-PLA-89-0.0/T8.5 ACST-P089(102) P-P089(102) Progress payment No. 037 Payment period ending: 07-20-17 ROAD & HIGHWAY BUILDERS LLC PO BOX 70846 RENO NV 89570 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 28,250,873.15 1,032,517.68 2. a. Extra Work 1,456,666.85 67,911.01 b. Adustment Comp. -969,744.40 -17,483.31 3. Materials on Hand 0.00 -116,148.80 4. Earned Subject to Retention 28,737,795.60 966,796.58 5. Mobilization 3,400,000.00 0.00 6. Total Work Completed 32,137,795.60 7. Deductions -5,372.40 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 32,132,423.20 966,796.58 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 966,796.58