Dept. of Trans. PROGRESS Serial No. Contract No. 08-201-14-02 03-2C8434 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 7% 12% 03-SAC-5501 Federal Project: NONE Progress payment No. 02 Payment period ending: 07-18-08 ALLEN L BENDER INC 2798 INDUSTRIAL BOULEVARD WEST SACRAMENTO CA 95691 Escrow No. 02371 Total Estimate This Estimate 1. Contract Itms Without Mobil. 721,565.40 426,841.50 2.a. Extra Work 16,308.77 16,308.77 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 737,874.17 443,150.27 5. Mobilization 6. Total Work Completed 737,874.17 7. Deductions -10,000.00 -10,000.00 8. a.Contract Retentions -73,787.42 -44,315.03 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 654,086.75 388,835.24 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 388,835.24