Dept. of Trans. PROGRESS Serial No. Contract No. 06-356-15-53 03-2C84U4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 9% 20% 03-SAC-5501 Federal Project: NONE Progress payment No. 03 Payment period ending: 12-20-06 DUAL CAL BUILDERS INC P O BOX 1160 CARMICHAEL CA 95609 Escrow No. 02271 Total Estimate This Estimate 1. Contract Itms Without Mobil. 398,156.77 326,726.29 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 398,156.77 326,726.29 5. Mobilization 6. Total Work Completed 398,156.77 7. Deductions -84,295.28 -84,295.28 8. a.Contract Retentions -39,815.68 -32,672.63 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 274,045.81 209,758.38 10. Reduction Amt to Escrow 11. Payment to Escrow 39,810.00 12. Net Pymt. this Estimate 209,758.38