Dept. of Trans. PROGRESS Serial No. Contract No. 10-298-12-47 03-2C8604 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 18% 23% 03-PLA-80-R56.1/R66.3 Federal Project: ACIM-000C(309) Progress payment No. 06 Payment period ending: 10-20-10 TEICHERT CONSTRUCTION P O BOX 276830 SACRAMENTO CA 95827 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 8,556,410.15 2,352,539.03 2.a. Extra Work 93,840.75 72,699.27 b. Adjustment Comp. 1,020,927.12 26,590.51 3. Materials on Hand 11,134.65 11,134.65 4. Earned Subject to Retention 9,682,312.67 2,462,963.46 5. Mobilization 6,525,000.00 2,175,000.00 6. Total Work Completed 16,196,178.02 7. Deductions -52,050.00 720,830.37 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 16,155,262.67 5,358,793.83 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 5,358,793.83