Dept. of Trans. PROGRESS Serial No. Contract No. 14-057-10-41 03-2C8604 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 99% 100% 03-PLA-80-R56.1/R66.3 Federal Project: ACIM-000C(309) Progress payment No. 46 Payment period ending: 02-20-14 TEICHERT CONSTRUCTION 4401 DULUTH AVENUE ROCKLIN, CA 95765 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 75,704,048.35 -208,082.98 2.a. Extra Work 3,886,990.24 566,182.18 b. Adjustment Comp. 3,900,608.20 -74,491.22 3. Materials on Hand 4. Earned Subject to Retention 83,491,646.79 283,607.98 5. Mobilization 8,700,000.00 0.00 6. Total Work Completed 92,191,646.79 7. Deductions -204,588.01 -5,750.30 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 91,987,058.78 277,857.68 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 277,857.68