Dept. of Trans. PROGRESS Serial No. Contract No. 07-297-11-07 03-2E1304 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 97% 99% 03-SAC-50-R9.5/R10.9 Federal Project: NONE Progress payment No. 08 Payment period ending: 10-19-07 SIERRA NEVADA CONSTRUCTION INC P O BOX 50760 SPARKS NV 89435 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2,751,906.29 47,540.60 2.a. Extra Work 302.39 0.00 b. Adjustment Comp. -45,488.00 -45,488.00 3. Materials on Hand 4. Earned Subject to Retention 2,706,720.68 2,052.60 5. Mobilization 77,816.85 0.00 6. Total Work Completed 2,784,537.53 7. Deductions -64,019.81 0.00 8. a.Contract Retentions -135,336.03 -102.63 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 2,585,181.69 1,949.97 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,949.97