Dept. of Trans. SEMI-FINAL Serial No. Contract No. 06-320-18-00 03-2E2104 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 03-ED-49-21.5/ .0 Federal Project: ACST-43A3(4) P-43A3(4) Progress payment No. 04 Payment period ending: 08-21-06 YUBACON INC P O BOX 3176 DIAMOND SPRINGS CA 95619 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 354,016.04 0.00 2.a. Extra Work 15,897.98 0.00 b. Adjustment Comp. -183.89 0.00 3. Materials on Hand 4. Earned Subject to Retention 369,730.13 0.00 5. Mobilization 6. Total Work Completed 369,730.13 7. Deductions -2,000.00 10,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 367,730.13 10,000.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 10,000.00