Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 07-116-19-16 03-2E2504 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 03-NEV-49-2.1/R13.2 Federal Project: NONE Progress payment No. 05 Payment period ending: 03-22-07 LINEAR OPTIONS INC 1 KELLY CT MENLO PARK CA 94025 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 312,097.96 1,750.00 2.a. Extra Work b. Adjustment Comp. 143,128.00 0.00 3. Materials on Hand 4. Earned Subject to Retention 455,225.96 1,750.00 5. Mobilization 6. Total Work Completed 455,225.96 7. Deductions -5,000.00 0.00 8. a.Contract Retentions -22,673.80 0.00 b. Unsatisfactory Prog. 0.00 1,685.67 c. Reduction after 95% Comp. 22,673.80 22,673.80 9. Total pay to Contractor 450,225.96 26,109.47 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 26,109.47