Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 06-318-18-45 03-2E6404 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 03-ED-50-20.9/37.5 Federal Project: NONE Progress payment No. 02 Payment period ending: 10-09-06 RON HALE CONSTRUCTION INC P O BOX 795 SHASTA LAKE CA 96019 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 596,459.00 356,897.00 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 596,459.00 356,897.00 5. Mobilization 6. Total Work Completed 596,459.00 7. Deductions -10,000.00 -10,000.00 8. a.Contract Retentions -11,978.10 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 11,978.10 11,978.10 9. Total pay to Contractor 586,459.00 358,875.10 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 358,875.10