Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 06-353-12-39 03-2E7104 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 03-ED-50-40.6/ .0 Federal Project: ACNH-43A9(4) Progress payment No. 03 Payment period ending: 12-05-06 R A NEMETZ CONSTRUCTION CO INC P O BOX 32 WILTON CA 95693 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 562,904.00 2,660.00 2.a. Extra Work 18,751.80 14,553.32 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 581,655.80 17,213.32 5. Mobilization 6. Total Work Completed 581,655.80 7. Deductions -1,000.00 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 580,655.80 17,213.32 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 17,213.32