Dept. of Trans. SEMI-FINAL Serial No. Contract No. 08-196-14-33 03-2E9604 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 03-ED-50-33.3/55.3 Federal Project: ACNH-43C6(4) Progress payment No. 03 Payment period ending: 05-22-08 DOUG VEERKAMP GENERAL ENGINEERING INC 2585 COLD SPRINGS ROAD PLACERVILLE CA 95667 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 96,967.32 0.00 2.a. Extra Work 399.23 399.23 b. Adjustment Comp. 891.48 0.00 3. Materials on Hand 4. Earned Subject to Retention 98,258.03 399.23 5. Mobilization 6. Total Work Completed 98,258.03 7. Deductions -2,433.55 10,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 95,824.48 10,399.23 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 10,399.23