Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 13-007-14-23 03-2F0204 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 03-ED-50-R3.5/17.0 Federal Project: NGP0-5012(7E) Progress payment No. 07 Payment period ending: 12-07-12 DESILVA GATES CONSTRUCTION LP P O BOX 2909 DUBLIN CA 94568 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 5,117,375.46 69,123.36 2.a. Extra Work 10,953.08 0.00 b. Adjustment Comp. -5,277.30 -5,277.30 3. Materials on Hand 4. Earned Subject to Retention 5,123,051.24 63,846.06 5. Mobilization 635,000.00 0.00 6. Total Work Completed 5,758,051.24 7. Deductions -49,050.00 -22,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 5,709,001.24 41,846.06 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 41,846.06