Dept. of Trans. PROGRESS Serial No. Contract No. 12-235-11-45 03-2F0304 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 82% 53% 03-PLA-80-5.1/14.5 Federal Project: IM08-324(0E) Progress payment No. 04 Payment period ending: 08-20-12 GRANITE CONSTRUCTION COMPANY P O BOX 50085 WATSONVILLE CA 95077 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 4,881,239.65 2,603,050.02 2.a. Extra Work b. Adjustment Comp. -45,330.40 -45,330.40 3. Materials on Hand 4. Earned Subject to Retention 4,835,909.25 2,557,719.62 5. Mobilization 130,298.10 6,514.91 6. Total Work Completed 4,966,207.35 7. Deductions -679,262.51 -679,262.51 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 4,286,944.84 1,884,972.02 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,884,972.02