Dept. of Trans. PROGRESS Serial No. Contract No. 12-326-11-01 03-2F0304 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 94% 98% 03-PLA-80-5.1/14.5 Federal Project: IM08-324(0E) Progress payment No. 08 Payment period ending: 11-20-12 GRANITE CONSTRUCTION COMPANY P O BOX 50085 WATSONVILLE CA 95077 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 5,508,090.09 40,206.00 2.a. Extra Work 90,183.12 0.00 b. Adjustment Comp. -45,330.40 0.00 3. Materials on Hand 4. Earned Subject to Retention 5,552,942.81 40,206.00 5. Mobilization 130,298.10 0.00 6. Total Work Completed 5,683,240.91 7. Deductions -25,315.49 -23,315.49 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 5,657,925.42 16,890.51 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 16,890.51