Dept. of Trans. PROGRESS Serial No. Contract No. 12-142-11-40 03-2F0404 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 74% 48% 03-SAC-80-12.5/18.0 Federal Project: IM08-324(1E) Progress payment No. 04 Payment period ending: 05-17-12 DESILVA GATES CONSTRUCTION P O BOX 2909 DUBLIN CA 94568 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 4,194,442.60 1,726,797.40 2.a. Extra Work 900.00 0.00 b. Adjustment Comp. -70,855.64 -70,855.64 3. Materials on Hand 4. Earned Subject to Retention 4,124,486.96 1,655,941.76 5. Mobilization 640,000.00 32,000.00 6. Total Work Completed 4,764,486.96 7. Deductions -2,000.00 -2,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 4,762,486.96 1,685,941.76 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,685,941.76