Dept. of Trans. PROGRESS Serial No. Contract No. 19-274-15-08 03-2F0804 PROGRESS PAYMENT VOUCHER %complete: %time: 90% 99% Location: Federal Project: 03-YUB-20-0.0/3.3 ACNH-X115(13) Progress payment No. 010 Payment period ending: 09-20-19 DREAMBUILDER CONSTRUCTION CORP 18543 YORBA LINDA BLVD #376 YORBA LINDA CA 92886 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2,847,571.14 168,226.57 2. a. Extra Work 255,615.36 -30,395.53 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 3,103,186.50 137,831.04 5. Mobilization 325,000.00 0.00 6. Total Work Completed 3,428,186.50 7. Deductions -32,760.00 -32,760.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 3,395,426.50 105,071.04 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 105,071.04