Dept. of Trans. PROGRESS Serial No. Contract No. 19-235-15-25 03-2F1304 PROGRESS PAYMENT VOUCHER %complete: %time: 48% 43% Location: Federal Project: 03-ED-50-39.5/48.7 ACNH-P050(146) Progress payment No. 004 Payment period ending: 08-20-19 MARTIN BROTHERS CONSTRUCTION 8801 FOLSOM BLVD #260 SACRAMENTO CA 95826 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 780,958.26 545,195.11 2. a. Extra Work 370.27 370.27 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 781,328.53 545,565.38 5. Mobilization 145,350.00 30,600.00 6. Total Work Completed 926,678.53 7. Deductions -10,000.00 -10,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 916,678.53 566,165.38 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 566,165.38