Dept. of Trans. PROGRESS Serial No. Contract No. 14-204-09-36 03-2F1504 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 83% 91% 03-ED-49-30.9/31.3 Federal Project: SSTP-P049(154) Progress payment No. 03 Payment period ending: 07-17-14 SIERRA NEVADA CONSTRUCTION INC P O BOX 50760 SPARKS NV 89435 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 817,787.53 475,285.51 2.a. Extra Work b. Adjustment Comp. -9,783.20 -9,783.20 3. Materials on Hand 4. Earned Subject to Retention 808,004.33 465,502.31 5. Mobilization 6. Total Work Completed 808,004.33 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 808,004.33 465,502.31 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 465,502.31