Dept. of Trans. PROGRESS Serial No. Contract No. 14-234-10-28 03-2F1504 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 94% 98% 03-ED-49-30.9/31.3 Federal Project: SSTP-P049(154) Progress payment No. 04 Payment period ending: 08-20-14 SIERRA NEVADA CONSTRUCTION INC P O BOX 50760 SPARKS NV 89435 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 933,752.08 115,964.55 2.a. Extra Work 34,996.39 34,996.39 b. Adjustment Comp. -2,388.20 7,395.00 3. Materials on Hand 4. Earned Subject to Retention 966,360.27 158,355.94 5. Mobilization 6. Total Work Completed 966,360.27 7. Deductions -3,000.00 -3,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 963,360.27 155,355.94 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 155,355.94