Dept. of Trans. PROGRESS Serial No. Contract No. 19-238-15-50 03-2F3204 PROGRESS PAYMENT VOUCHER %complete: %time: 29% 36% Location: Federal Project: 03-YUB-20-8.0/10.2 B1NH-P020(186) Progress payment No. 006 Payment period ending: 08-20-19 LAMON CONSTRUCTION CO INC 871 VON GELDERN WAY YUBA CITY CA 95991 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2,121,595.61 224,791.55 2. a. Extra Work 4,950.00 4,950.00 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 2,126,545.61 229,741.55 5. Mobilization 179,075.00 0.00 6. Total Work Completed 2,305,620.61 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 2,305,620.61 229,741.55 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 229,741.55