Dept. of Trans. PROGRESS Serial No. Contract No. 20-240-12-18 03-2F3404 PROGRESS PAYMENT VOUCHER %complete: %time: 59% 85% Location: Federal Project: 03-PLA-49-3.1/7.5 B1NH-P049(177) Progress payment No. 015 Payment period ending: 08-20-20 FLATIRON WEST, INC. 1770 LA COSTA MEADOWS DR SAN MARCOS CA 92078 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 7,357,435.63 -1,654,061.38 2. a. Extra Work 3,656,313.70 3,352,350.59 b. Adustment Comp. 975,099.47 135,294.05 3. Materials on Hand 997,322.78 -521,125.14 4. Earned Subject to Retention 12,986,171.58 1,312,458.12 5. Mobilization 2,622,000.00 0.00 6. Total Work Completed 14,610,848.80 7. Deductions -20,000.00 -2,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 15,588,171.58 1,310,458.12 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,310,458.12