Dept. of Trans. PROGRESS Serial No. Contract No. 20-267-12-59 03-2F3404 PROGRESS PAYMENT VOUCHER %complete: %time: 56% 91% Location: Federal Project: 03-PLA-49-3.1/7.5 B1NH-P049(177) Progress payment No. 016 Payment period ending: 09-20-20 FLATIRON WEST, INC. 1770 LA COSTA MEADOWS DR SAN MARCOS CA 92078 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 6,562,081.70 -795,353.93 2. a. Extra Work 5,328,369.96 1,672,056.26 b. Adustment Comp. 975,099.47 0.00 3. Materials on Hand 970,448.64 -26,874.14 4. Earned Subject to Retention 13,835,999.77 849,828.19 5. Mobilization 2,760,000.00 138,000.00 6. Total Work Completed 15,625,551.13 7. Deductions -30,000.00 -10,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 16,565,999.77 977,828.19 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 977,828.19