Dept. of Trans. SEMI-FINAL Serial No. Contract No. 22-245-06-34 03-2F3404 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 03-PLA-49-3.1/7.5 B1NH-P049(177) Progress payment No. 036 Payment period ending: 03-15-22 FLATIRON WEST, INC. 2100 GOODYEAR RD BENICIA CA 94510 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 14,547,098.00 0.00 2. a. Extra Work 15,874,724.86 43,052.67 b. Adustment Comp. 854,458.16 0.00 3. Materials on Hand 4. Earned Subject to Retention 31,276,281.02 43,052.67 5. Mobilization 2,760,000.00 0.00 6. Total Work Completed 34,036,281.02 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 34,036,281.02 43,052.67 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 43,052.67