Dept. of Trans. PROGRESS Serial No. Contract No. 21-322-14-05 03-2F5704 PROGRESS PAYMENT VOUCHER %complete: %time: 53% 48% Location: Federal Project: 03-PLA-80-46.3/R63.5 ACIM-080-4(207) Progress payment No. 010 Payment period ending: 11-20-21 WALSH CONSTRUCTION COMPANY II LLC 1390 WILLOW PASS RD #950 CONCORD CA 94520 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 12,665,291.66 1,018,555.45 2. a. Extra Work 221,362.22 56,302.33 b. Adustment Comp. 3. Materials on Hand 593,992.00 -504,185.00 4. Earned Subject to Retention 13,480,645.88 570,672.78 5. Mobilization 2,755,000.00 0.00 6. Total Work Completed 15,641,653.88 7. Deductions -72,594.20 -10,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 16,163,051.68 560,672.78 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 560,672.78