Dept. of Trans. PROGRESS Serial No. Contract No. 22-168-13-47 03-2F5704 PROGRESS PAYMENT VOUCHER %complete: %time: 65% 62% Location: Federal Project: 03-PLA-80-46.3/R63.5 ACIM-080-4(207) Progress payment No. 017 Payment period ending: 06-20-22 WALSH CONSTRUCTION COMPANY II LLC 1390 WILLOW PASS RD #950 CONCORD CA 94520 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 15,899,039.10 745,583.65 2. a. Extra Work 737,521.70 9,682.52 b. Adustment Comp. 161,367.74 0.00 3. Materials on Hand 2,163,114.00 613,289.00 4. Earned Subject to Retention 18,961,042.54 1,368,555.17 5. Mobilization 2,900,000.00 0.00 6. Total Work Completed 19,697,928.54 7. Deductions -42,594.20 -10,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 21,818,448.34 1,358,555.17 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,358,555.17