Dept. of Trans. PROGRESS Serial No. Contract No. 22-259-12-44 03-2F5704 PROGRESS PAYMENT VOUCHER %complete: %time: 83% 86% Location: Federal Project: 03-PLA-80-46.3/R63.5 ACIM-080-4(207) Progress payment No. 020 Payment period ending: 09-20-22 WALSH CONSTRUCTION COMPANY II LLC 1390 WILLOW PASS RD #950 CONCORD CA 94520 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 21,097,375.97 1,505,101.31 2. a. Extra Work 903,623.07 50,242.35 b. Adustment Comp. 422,976.56 107,170.98 3. Materials on Hand 317,366.00 -882,549.00 4. Earned Subject to Retention 22,741,341.60 779,965.64 5. Mobilization 2,900,000.00 0.00 6. Total Work Completed 25,323,975.60 7. Deductions -47,594.20 -5,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 25,593,747.40 774,965.64 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 774,965.64