Dept. of Trans. SUPPLEMENTAL Serial No. Contract No. 22-346-10-36 03-2F5704 PROGRESS PAYMENT VOUCHER %complete: %time: 92% 92% Location: Federal Project: 03-PLA-80-46.3/R63.5 ACIM-080-4(207) Progress payment No. 023 Payment period ending: 11-20-22 WALSH CONSTRUCTION COMPANY II LLC 1390 WILLOW PASS RD #950 CONCORD CA 94520 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 23,740,342.92 383,912.46 2. a. Extra Work 1,208,402.29 36,500.00 b. Adustment Comp. 579,655.59 -50,123.26 3. Materials on Hand 34,318.00 0.00 4. Earned Subject to Retention 25,562,718.80 370,289.20 5. Mobilization 2,900,000.00 0.00 6. Total Work Completed 28,428,400.80 7. Deductions -67,594.20 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 28,395,124.60 370,289.20 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 370,289.20