Dept. of Trans. PROGRESS Serial No. Contract No. 12-205-12-41 03-2F5804 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 37% 30% 03-SIE-89-0.0/15.0 Federal Project: STP-P089(101) Progress payment No. 03 Payment period ending: 07-19-12 TEICHERT CONSTRUCTION 4401 DULUTH AVENUE ROSEVILLE CA 95678 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,596,592.03 1,521,790.53 2.a. Extra Work 11,720.06 8,897.00 b. Adjustment Comp. 28,287.00 28,287.00 3. Materials on Hand 4. Earned Subject to Retention 1,636,599.09 1,558,974.53 5. Mobilization 475,000.00 475,000.00 6. Total Work Completed 2,111,599.09 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 2,111,599.09 2,033,974.53 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 2,033,974.53