Dept. of Trans. PROGRESS Serial No. Contract No. 12-326-08-35 03-2F6704 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 87% 90% 03-YOL-113-R0.3/R10.3 Federal Project: NONE Progress payment No. 02 Payment period ending: 11-20-12 QUIMU CONTRACTING INC PO BOX 1177 DIXON, CA 95620 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 266,909.05 98,031.60 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 266,909.05 98,031.60 5. Mobilization 6. Total Work Completed 266,909.05 7. Deductions -5,000.00 -5,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 261,909.05 93,031.60 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 93,031.60