Dept. of Trans. PROGRESS Serial No. Contract No. 20-268-10-39 03-2F9804 PROGRESS PAYMENT VOUCHER %complete: %time: 80% 75% Location: Federal Project: 03-COL-20-31.8/32.8 B1NH-P020(187) Progress payment No. 010 Payment period ending: 09-20-20 TEICHERT CONSTRUCTION PO BOX 13557 SACRAMENTO CA 95853 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 9,495,733.54 1,620,408.86 2. a. Extra Work 360,465.46 44,595.37 b. Adustment Comp. 145,718.21 0.00 3. Materials on Hand 0.00 -101,804.25 4. Earned Subject to Retention 10,001,917.21 1,563,199.98 5. Mobilization 1,164,389.50 0.00 6. Total Work Completed 11,166,306.71 7. Deductions -26,000.00 -10,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 11,140,306.71 1,553,199.98 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,553,199.98