Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 21-350-16-40 03-2G0804 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 03-COL-45-0.0/19.8 NONE Progress payment No. 003 Payment period ending: 09-24-21 S.T. RHOADES CONSTRUCTION INC. 8585 COMMERCIAL WAY REDDING CA 96002 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2,098,919.97 24,562.50 2. a. Extra Work 4,673.59 4,673.59 b. Adustment Comp. 42,317.44 42,317.44 3. Materials on Hand 4. Earned Subject to Retention 2,145,911.00 71,553.53 5. Mobilization 6. Total Work Completed 2,145,911.00 7. Deductions -20,000.00 -20,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 2,125,911.00 51,553.53 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 51,553.53