Dept. of Trans. PROGRESS Serial No. Contract No. 23-206-07-21 03-2G5604 PROGRESS PAYMENT VOUCHER %complete: %time: 82% 85% Location: Federal Project: 03-VAR NONE Progress payment No. 005 Payment period ending: 07-20-23 HIGHWAY SPECIALTY COMPANY INC PO BOX 141 PALO CEDRO CA 96073 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 737,350.00 68,140.00 2. a. Extra Work 5,311.59 0.00 b. Adustment Comp. 3. Materials on Hand 0.00 -47,684.00 4. Earned Subject to Retention 742,661.59 20,456.00 5. Mobilization 28,351.00 0.00 6. Total Work Completed 771,012.59 7. Deductions -1,000.00 -1,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 770,012.59 19,456.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 19,456.00