Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 23-325-08-00 03-2G6004 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 03-BUT-99-R34.3 NONE Progress payment No. 002 Payment period ending: 10-13-23 DEES BURKE ENGINEERING CONSTRUCTORS LLC 207 W STATE ST ONTARIO CA 91762 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 461,001.92 9,531.00 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 461,001.92 9,531.00 5. Mobilization 70,000.00 0.00 6. Total Work Completed 531,001.92 7. Deductions -30,000.00 -7,868.44 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 501,001.92 1,662.56 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,662.56