Dept. of Trans. PROGRESS Serial No. Contract No. 23-229-08-38 03-2G6604 PROGRESS PAYMENT VOUCHER %complete: %time: 91% 56% Location: Federal Project: 03-BUT-162-20.7/23.3 NONE Progress payment No. 001 Payment period ending: 08-20-23 SAK CONSTRUCTION LLC PO BOX 71129 CHICAGO IL 60694 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 328,210.20 328,210.20 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 328,210.20 328,210.20 5. Mobilization 6. Total Work Completed 328,210.20 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 328,210.20 328,210.20 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 328,210.20