Dept. of Trans. PROGRESS Serial No. Contract No. 22-053-15-00 03-2H2404 PROGRESS PAYMENT VOUCHER %complete: %time: 6% 37% Location: Federal Project: 03-BUT-32-7.6/7.9 HSNH-P032(49) Progress payment No. 004 Payment period ending: 02-20-22 LAMON CONSTRUCTION CO INC 871 VON GELDERN WAY YUBA CITY CA 95991 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 40,728.44 0.00 2. a. Extra Work 11,653.70 0.00 b. Adustment Comp. 3. Materials on Hand 260,620.21 201,410.64 4. Earned Subject to Retention 313,002.35 201,410.64 5. Mobilization 142,500.00 142,500.00 6. Total Work Completed 194,882.14 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 455,502.35 343,910.64 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 343,910.64