Dept. of Trans. PROGRESS Serial No. Contract No. 20-325-10-44 03-2H57U4 PROGRESS PAYMENT VOUCHER %complete: %time: 39% 25% Location: Federal Project: 03-VAR NONE Progress payment No. 003 Payment period ending: 11-20-20 PTM GENERAL ENGINEERING SERVICES INC PO BOX 7745 RIVERSIDE CA 92513 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 830,980.00 189,860.00 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 830,980.00 189,860.00 5. Mobilization 95,037.05 0.00 6. Total Work Completed 926,017.05 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 926,017.05 189,860.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 189,860.00