Dept. of Trans. PROGRESS Serial No. Contract No. 22-112-14-20 03-2H6304 PROGRESS PAYMENT VOUCHER %complete: %time: 10% 0% Location: Federal Project: 03-BUT-162-18.4/19.9 HSST-P162(42) Progress payment No. 004 Payment period ending: 04-20-22 DESILVA GATES CONSTRUCTION LP 11555 DUBLIN BLVD DUBLIN CA 94568 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 439,366.68 104,246.34 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 147,980.32 -10,225.68 4. Earned Subject to Retention 587,347.00 94,020.66 5. Mobilization 400,000.00 0.00 6. Total Work Completed 839,366.68 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 987,347.00 94,020.66 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 94,020.66