Dept. of Trans. PROGRESS Serial No. Contract No. 17-299-13-20 03-2H9104 PROGRESS PAYMENT VOUCHER %complete: %time: 62% 67% Location: Federal Project: 03-VAR NONE Progress payment No. 003 Payment period ending: 10-20-17 TEICHERT CONSTRUCTION 4401 DULUTH AVE ROCKLIN CA 95765 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2. a. Extra Work 883,496.20 19,857.40 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 883,496.20 19,857.40 5. Mobilization 6. Total Work Completed 883,496.20 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 883,496.20 19,857.40 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 19,857.40