Dept. of Trans. PROGRESS Serial No. Contract No. 17-202-11-01 03-2H9204 PROGRESS PAYMENT VOUCHER %complete: %time: 54% 87% Location: Federal Project: 03-NEV-49-14.0/R14.1 NONE Progress payment No. 002 Payment period ending: 07-20-17 GRANITE CONSTRUCTION COMPANY 585 WEST BEACH ST WATSONVILLE CA 95076 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2. a. Extra Work 371,879.58 64,669.23 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 371,879.58 64,669.23 5. Mobilization 6. Total Work Completed 371,879.58 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 371,879.58 64,669.23 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 64,669.23