Dept. of Trans. PROGRESS Serial No. Contract No. 23-262-13-51 03-2J7604 PROGRESS PAYMENT VOUCHER %complete: %time: 37% 52% Location: Federal Project: 03-SAC-5-22.8/23.7 NONE 03-SAC-51-5.2/5.8 Progress payment No. 003 Payment period ending: 09-20-23 PACIFIC INFRASTRUCTURE CONSTRUCTION LLC 871 COTTING CT #A VACAVILLE CA 95688 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,425,225.10 884,575.10 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 0.00 -176,268.75 4. Earned Subject to Retention 1,425,225.10 708,306.35 5. Mobilization 494,000.00 104,000.00 6. Total Work Completed 1,919,225.10 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 1,919,225.10 812,306.35 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 812,306.35